Presentation of the project

Runtime

3 months

End date of realization

10/11/2014

Construction and rehabilitation of the landfill in the province of IFRANE

Environnemental Project

  • Construction of buildings housing the technical areas
  • Construction of leachate ponds
  • Construction of draining structures and sanitation works in concrete treated against leachate

Elements of the environmental aspect

  • Treatment plant wastewater ;
  • Basin storage and treatment of leachate ;
  • Retention basin against erosion ;
  • Sewerage network ;
  • Bank stabilization of wadis and embankments ;
  • Alternative products, geo-synthetic, anti-contaminants and geo-composite drainage.

Gallery

TOP
EnglishFrench